For this $3.1 million project with the San Francisco Transportation Agency and Square, CBI was charged with the decommissioning of the existing Bank of America Critical Data Center 6th floor. This consisted of:
- A complete demolition back to warm shell of the 6th floor
- Modifications to existing utilities and devices to accommodate the demolition
- New acoustical ceilings throughout
- Conversion of the Level 6 Pre-Action control stations to a new wet-pipe fire sprinkler system
- Installation of new electrical throughout including lighting
- Installation of fire alarm systems
- Removal of the exterior pre-cast concrete wall panels to allow for their replacement with new concrete bulkheads, header and new glass window systems
We established a tight system of on-going communication and coordination with multiple departments within the City and County of San Francisco, Hudson Pacific Properties, the SFMTA, Square, architects and subcontractors, to deliver the project on time and within budget.